Progress continues at the Wayne Memorial Hospital jobsite with the following activities:

  • Stair 1 erection is in progress
  • 1st & 4th Floors – interior metal stud framing in progress
    MEP rough-in on 1st, 3rd, 4th, 5th and Penthouse Floors
  • Connecting bridge framing is in progress
  • 4th Floor corridor top-out & fire/smoke sealing is in progress
  • Exterior framing & sheathing on the 4th, 5th & Penthouse Floors
  • Air barrier installation on the 4th & 5th Floors
  • Brick is being set at the 3rd Floor along the South elevation
  • Roofing installation at the main roof

 

 

 