Wayne Memorial Hospital Addition & Renovation – Construction Update

Excavation and installation of  the sanitation and sewer lines continue. Concrete footings, piers and walls for the main Addition are completed. Foundation waterproofing, dampproofing and backfill  are complete. First floor slab-on-grade prep and under-slab rough-in has begun.  On June 25, 2018, the final steel beam was lifted and set into the new patient tower. Metal decking on the new Addition is being installed.  Renovation work inside the hospital has been completed in three areas.

 

 